RIBA stages through to practical completion. 50 tasks across 7 phases - including procurement, tender, building control inspections, and snagging.

50
Tasks
7
Phases
26
Weeks
Get Solo - £9.99 →

All 8 templates + exports included

← All templates
Construction Project template open in Gantto
Screenshot coming soon
What's included

Every task. Nothing missed.

Built from research into what real construction actually requires. Delete what doesn't apply - the value is in the tasks you didn't think of.

Phase 01
Design & Planning
  • Client brief & project objectives
  • Appoint design team
  • Site surveys (topographic, ground investigation)
  • Asbestos & environmental surveys
  • RIBA Stage 1 - Preparation
  • RIBA Stage 2 - Concept design
  • RIBA Stage 3 - Developed design
  • Submit planning application
  • ◆ Planning permission granted
  • Building regulations submission
  • RIBA Stage 4 - Technical design
Phase 02
Procurement
  • Tender documents prepared
  • Tender issued to contractors
  • Tender returns & assessment
  • Contractor appointed
  • ◆ Contract signed
  • Long-lead items ordered
Phase 03
Groundwork & Substructure
  • Site setup, hoarding & welfare
  • Demolition (if applicable)
  • Bulk excavation
  • Drainage & below-ground services
  • Pile caps / ground beams
  • Ground floor slab
  • Building control substructure inspection
Phase 04
Superstructure
  • Structural frame / steel erection
  • Brickwork / external walls
  • Roof structure
  • Roof covering & weatherproofing
  • External windows & doors
  • ◆ Building watertight
Phase 05
MEP First Fix
  • Mechanical first fix
  • Electrical first fix
  • Plumbing first fix
  • HVAC / ventilation ductwork
  • Underfloor heating (if applicable)
  • Building control first fix inspection
Phase 06
Fit-Out
  • Dry lining & partition walls
  • Plastering
  • Plaster & screed drying
  • MEP second fix
  • Internal joinery & finishes
  • Flooring
  • Decoration
  • External works & landscaping
Phase 07
Handover
  • Building control final inspection
  • Commissioning & testing
  • Snagging survey
  • Snagging resolution
  • Collect all certificates & warranties
  • ◆ Practical completion

Why use Gantto
for construction?

MS Project is the industry standard but costs hundreds of pounds a year. Gantto does the core job - critical path, trade sequencing, milestone tracking - for free, in a browser, with no install.

Share the plan with your contractor, QS, or client as a file. No login required on their end.

Full RIBA stage structure built in from Stage 1 to handover
Procurement and tender process tracked alongside design
Building control inspection milestones at every key stage
Trade dependencies enforced - correct sequence, every time
Asbestos and environmental surveys included as tasks
Export to PDF and share with client or funder

Your build.
Your programme.

Open the template, set your start on site date, and adjust the phase durations to your project. The dependencies handle the sequence automatically.